Please be advised there will be road work on various streets in the Pearl City areas as shown above. The work primarily consists of milling and resurfacing the asphalt roadway. Additional activities include installation of permanent pavement markings, traffic loop sensors, and adjustment of utility manholes. The construction work is tentatively scheduled to begin on July 30, 2007 with a contract duration of 155 calendar days. The work hours will be from 8:30 a.m. to 3:30 p.m., Monday through Friday (with possible weekend work). Motorists are advised to allow extra travel time while driving through the work areas. Please observe all traffic controls and posted signs; expect lane closures and delays.
Grace Pacific Corporation
Phone: 842-3223
(SB05531001 7/22, 7/23, 7/24/07)